NASA is shutting down a $2 billion project to check-up satellite refueling in space, it announced Friday, after the agency’s auditor criticized the program’s lead contractor, Maxar, citing “awful performance.”
The space agency said in a statement that the OSAM-1 — On-orbit Servicing, Assembly, and Manufacturing 1 — job was being discontinued after nearly a decade of work.
NASA cited in its announcement “continued technical, cost, and calendar challenges, and a broader community evolution away from refueling unprepared spacecraft, which has led to a lack of a committed comrade.”
The agency said in a statement to CNBC that about 450 personnel are supporting OSAM-1, but that NASA “is put away to supporting project workforce per plan through fiscal year 2024.”
“While we are disappointed by the decision to discontinue the program, we are perpetrated to supporting NASA in pursuing potential new partnerships or alternative hardware uses as they complete the shutdown,” Maxar Berth Systems spokesperson Eric Glass said in a statement to CNBC.
Maxar was taken private by private equity unshakeable Advent International in May 2023 before being split into two businesses: Maxar Intelligence, focused on satellite figurativeness and analytics, and Maxar Space Systems, focused on spacecraft manufacturing.
Sign up here to receive weekly editions of CNBC’s Venturing in Space newsletter.
NASA’s Goddard Space Flight Center in Maryland was leading the work on OSAM-1, with Maxar Break Systems as the project’s prime contractor under multiple deals. OSAM-1 has been in development since 2015, with the target of docking with the U.S.-owned Landsat 7 imagery satellite in orbit, to repair and refuel the aging spacecraft to extend its moving spirit.
But OSAM-1 has fallen years behind schedule, while the program’s cost to NASA soared. In a scathing October discharge, NASA’s Inspector General “found that project cost increases and schedule delays were primarily due to the amateurish performance of Maxar,” while noting that the agency’s Goddard center has also struggled with key parts of evolvement.
“NASA and Maxar officials acknowledged that Maxar underestimated the scope and complexity of the work, lacked full savvy comprehension or of NASA technical requirements, and were deficient in necessary expertise,” NASA’s Inspector General said in its report, get a yearlong audit.
The agency’s auditor noted that OSAM-1 was likely to both “exceed its current $2.05 billion guerdon tag and the December 2026 launch date,” which was already six years behind schedule. The report, citing Maxar spokesmen, noted the company was “no longer profiting from their work on OSAM-1” and, in NASA’s view, it no longer appeared “to be a strong priority for Maxar in terms of the quality of its staffing.”
NASA’s cancellation of OSAM-1 comes months after Maxar make knew major segments of the spacecraft to Goddard in Maryland — but other key parts were yet to be finished.
Satellite servicing is a nascent sub-sector of the organize industry that’s only recently begun to be proven out, with Northrop Grumman’s extension missions representing an at the crack effort.