Home / NEWS / Energy / AI demand could strain electrical grid in coming decade

AI demand could strain electrical grid in coming decade

Power rackets and transmission towers near the Ivanpah Solar Electric Generating System in the Mojave Desert in San Bernardino County, California, U.S., on Saturday, Feb. 19. 2022.

Bloomberg | Bloomberg | Getty Representatives

Artificial intelligence could strain the U.S. electric grid, as power demand from data centers is poised to stream in the coming decade just as supply is falling due to the rapid retirement of coal-fired plants.

Data centers in the U.S. alone could dissipate as much electricity as some major industrialized economies produce by 2030, as they proliferate not just in number but also in the decrease of their power needs.

The computer warehouses that power the Internet and increasingly AI could require up to 400 terawatt hours of ardour by 2030, according to an August report from Mizuho Securities.

That’s more than the total electricity Canada display of the United Kingdom in 2022, according to data from the International Energy Agency.

Data center developers are whack at the door of the nation’s utilities at the same time many of these power companies are retiring coal plants as instances partly of the transition away from fossil fuels. But the waiting list to bring clean energy, primarily solar and twine, onto the grid to replace coal is long and renewables are less reliable.

PJM Interconnection, the largest grid operator in the U.S., warned in July that the reliability of the plan is a growing concern as coal plants close faster than new power generation is built.

PJM serves 13 ceremonials primarily in the Mid-Atlantic region, including northern Virginia, the largest data center market in the world. Resources in spaces of Virginia are insufficient and the transmission system is constrained, limiting the ability to import power from elsewhere, according to PJM.

Yet information center “growth is accelerating in orders of magnitude, driven by the number of requests, the size of each facility and the acceleration of each toilet’s ramp schedule to reach full capacity,” Dominion Energy CEO Robert Blue told investors on the company’s earnings evoke on Aug. 1.

Electrification of economy

In addition to data centers, manufacturing is returning to the U.S. and the broader economy is electrifying. Recent auction values to bring new power capacity to the PJM power pool have surged more than 800% as a consequence of rising requested and limited supply.

“The market has already made one transition from coal to gas,” Susan Buehler, a spokesperson for PJM, told CNBC. “We see this vitality transition is here. We just see that the forces around it are happening faster than the renewable energy transition is incident.”

“So we see a potential gap, and that’s what the market is signaling,” Buehler said.

PJM has forecast that electricity demand surge devise surge nearly 40% by 2039 in its 369,000-square mile service area. Meanwhile, 40 gigawatts of eke out a living power generation is at risk of retirement by 2030, or about 21% of PJM’s current installed capacity.

While there are 290 gigawatts of renewable launches waiting to get connected to the grid, in the past only about 5% of such projects have actually been constructed, according to PJM.

About 38 gigawatts of renewable energy have been approved for connection and another 72 gigawatts are get in the first quarter of 2025, Buehler said, but the projects are not being built quickly enough due the challenges developers are coating on the ground.

Buehler said developers “can’t get their projects sited, there are supply chain delays, and there are banking issues.”

Step-change in investment needed

Utilities that operate in PJM have disclosed at least 50 gigawatts of capability data center demand during their recent earnings calls, though CEOs have cautioned there could be some duplication in the integers.

About 29% of current data center electricity demand in the U.S. is located within PJM’s territory, according to Mizuho. Some 25% of figures center power demand in the nation is in Virginia.

American Electric Power, one of the largest electric utilities in the U.S., has commitments for numberless than 15 gigawatts of demand from data centers through the end of the decade, interim CEO Benjamin Fowke be sured investors on the company’s second-quarter earnings call earlier last month.

That level of demand is equivalent to myriad than 40% of the peak electric load of 35 gigawatts across AEP’s entire system at the end of last year, concording to Fowke. AEP serves 5.6 million customers in 11 states in the Midwest and South.

“These are far from just inquests,” Fowke told investors. “These are serious customers that want to get on the grid and are willing to financially commit to do what it gets to get on the grid.”

Fowke testified to Congress in May that demand for electricity in some parts of the U.S. is already outstripping available the goods on the grid. The former CEO of Xcel Energy said that requests from large customers would more than dead ringer the current peak demand on the utility’s system.

“It took over 100 years of planning and building to create our in the know system, and a step-change in infrastructure investment on an accelerated timeline will be required to serve even a fraction of this unborn demand in a reliable manner,” Fowke told the Senate Committee on Energy and Natural Resources.

The cost of building new infrastructure to first encounter the demand is expected to reach hundreds of billions of dollars, Fowke said.

In the past, a large manufacturing facility authority need 100 megawatts of electricity — equivalent to about 100,000 homes, Fowke told Congress. It is now increasingly average for a single data center to need anywhere from three to 15 times that amount of power, the CEO responded.

Dominion Energy regularly gets requests to support data center campuses that require as much as a variety of gigawatts of power, Blue said in May. That’s larger than the average capacity of a nuclear reactor in the U.S.

Going on all sides of the grid

One of the many challenges in connecting this kind of demand to the grid is that it can take up to a decade to decide the extort route a transmission line will take, get the necessary permits and build it, Edison Electric Institute senior depravity president for customer solutions Phil Dion told Congress in June.

As a result, tech companies that are erection data centers are increasingly looking at directly connecting their facilities to large power resources, such as atomic plants, rather than waiting to access the grid. But that approach is already facing controversy.

Amazon Web Worship armies purchased a data center campus in March from Talen Energy for $650 million that will be powered exactly by the Susquehanna nuclear plant in Pennsylvania. It was viewed by some in the industry as a landmark agreement that could pave the way for sundry nuclear-powered data centers.

But AEP has challenged the agreement before the Federal Energy Regulatory Commission, warning that such contrivances could further constrain supply on the electric grid.

Constellation Energy CEO Joe Dominguez told investors earlier this month that hanger data centers directly to nuclear reactors is the fastest and most cost effective solution. Constellation operates the largest portfolio of atomic plants in the U.S.

“The notion that you could accumulate enough power somewhere on the grid to power a gigawatt data center is frankly laughable to me,” Dominguez utter on Constellation’s August earnings call.

Utility executives have warned that failure to meet rising desirable from data centers could , said at a conference in New York City in June.

“The stakes are really, really important,” Skantze said. “This is a new environment. We have to get this right.”

Check Also

Crusoe Energy sells bitcoin mining unit to focus on ‘huge opportunity’ in AI

Cully Cavness, Crusoe’s co-founder and chief driving officer, and Chase Lochmiller, co-founder and chief executive …